CNC Plasma Cutter Baileigh PT-22
Getting the new plasma cutter set up! Had to figure out how to get my air compressor up 8ft onto the mezzanine (it was interesting for sure). I also got the plasma table fixed and added a video for knowing which kind of proximity switch to buy PNP or NPN […]

Part 2 2×2 CNC Plasma Cutter






Steps to building a pole barn
We bring in the big(er) guns to work on the final grade, septic riser, and trenching for gutter drains. There will be a large driveway and we need to make sure there is enough drainage to get all the water out and away from the foundation and septic systems.

Progress Report 14 – 30×48′ Pole Barn build


Steps to building a pole barn 1
Picture dump! Lots of progress and projects since the last update. This time we get electrical, trenching, drainage, and I drag a bunch of junk home from FB Marketplace!

Progress Report 13 – 30×48′ Pole Barn build




Mini Boatside and Rock Sliders on Vitara Tracker
Finally, the last part of the rock slider build! Lets finish them up and see what they look like completed. The goal is to have some beefy nerf bars we can use to rub against rocks and still be able to open the doors after a long day of wheeling!

Part 3 – Mini Boatside and Rock Sliders on Vitara ...


Wheelchair platform for Transferring to Tall Trucks and Vans
Transferring from wheelchairs to taller vehicles like trucks and vans can sometimes be challenging due to differences in height. Wheelchair users cannot slide across using a transfer board and grab handles like they can with a car. This is a custom platform solution we came up with to put the […]

Wheelchair platform for Transferring to Tall Trucks and Vans



Steps to building a pole barn
Moving stuff in and starting to frame out the full bathroom! I share some valuable lessons that I learned while teaching myself how to frame a wall. I made some newbie mistakes, but I think it will work out in the end.

Progress Report 12 – 30×48′ Pole Barn build







Steps to building a pole barn
Today we finish up installing the foam, staple down the PEX tubing for the radiant heat, and set up the manifold. Also, the plumbers rough in for the shower, toilet, and sink!

Progress Report 9 – 30×48′ Pole Barn build